SunEast Hooversville Solar
10 MW generation in Somerset, PA · In queue since October 2019 · Proposed COD August 2026
10 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-08-01
The SunEast Hooversville Solar project is a proposed 10 MW solar generation project located in Somerset County, Pennsylvania. The project is in the PJM interconnection queue as entry AF2-002, with a queue entry date of October 1, 2019. The proposed commercial operation date is August 1, 2026. The project's interconnection agreement has been executed.
The project, which connects to the PENELEC utility grid at the Hooversville 115 kV III point of interconnection, is currently listed as suspended in the PJM queue. The developer is unknown. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Hooversville 115 kV III
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HOOVERSV115 KV 1 TX 1
- POI Substation
- Hooversville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SunEast Hooversville SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.