Harmony Plains Solar and Storage Facility
70 MW hybrid in Warren, NJ · In queue since October 2019 · Proposed COD March 2029
70 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Phase
COD target: 2029
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-03-28
The Harmony Plains Solar and Storage Facility is a proposed 70 MW hybrid solar and battery energy storage project located in Warren County, New Jersey. The project consists of 70 MW of solar generation. It is interconnected to the Jersey Central Power & Light (JCPL) system via the Merrill Creek 115 kV point of interconnection.
The project is listed in the PJM interconnection queue as entry AF1-320, with an original queue entry date of October 1, 2019. The proposed commercial operation date is December 28, 2026, and the project has an executed Interconnection Agreement (IA). The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
NRIS
Point of Interconnection
Merrill Creek 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MARTINSC18 KV LMB CC1
- POI Substation
- Merrill Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Harmony Plains Solar and Storage FacilityForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.