South Dixon Solar
200 MW generation in Lee, IL · In queue since September 2019 · Proposed COD December 2022
200 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Phase
COD target: 2022
Total Duration
3y 3m
Schedule
43 months past proposed COD
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AF1-280 is a proposed 200 MW solar generation project located in Lee County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2019. Its proposed commercial operation date is December 1, 2022.
Currently, the project's interconnection status is listed as "System Impact Study." The point of interconnection is the Nelson-Lee County area. The interconnecting utility is ComEd.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Deriva Energy Solar, LLC
Utility
ComEd
Entity
PJM
Service Type
ERIS
Point of Interconnection
Nelson-Lee County
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about South Dixon SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.