Pleasant Prairie Solar Energy Center
50 MW generation in Franklin, OH · In queue since September 2019 · Proposed COD December 2027
50 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Under Construction
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-30
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Pleasant Prairie Solar Energy Center is a proposed 50 MW solar generation project located in Franklin County, Ohio. The project is being developed within the PJM Interconnection queue under queue ID PJM-AF1-275. Its queue entry date is September 30, 2019, and the proposed commercial operation date is December 31, 2027. The project has an Interconnection Agreement (IA) that has been executed.
The proposed project is interconnected to the AEP utility system at the Cole 345 kV point of interconnection. The project consists of 50 MW of solar photovoltaic generation capacity. The project is currently listed as active within the PJM queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Cole 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- COLE 34.5 KV PLEPRASP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Prairie
Data-driven briefing on Prairie — fleet, generation, financial, and news signals.
Prairie Solar (VA)
Data-driven briefing on Prairie Solar — fleet, generation, financial, and news signals.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Pleasant Prairie Solar Energy Center