Hoodlebug Solar Energy Center
110 MW generation in Indiana, PA · In queue since October 2019 · Proposed COD August 2027
110 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-31
Interconnection Agreement executed per PJM queue status
The Hoodlebug Solar Energy Center is a proposed 110 MW solar generation project located in Indiana County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-272, with a queue entry date of October 1, 2019, and a proposed commercial operation date of August 31, 2027. The interconnection agreement for the project has been executed.
The proposed project, which will interconnect to the Lucerne 115 kV point of interconnection, is located within the PENELEC utility territory.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Lucerne 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LUCERNE 115 KV NO2 TX
- POI Substation
- Lucerne Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Hoodlebug Solar Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.