Lamberton Road Battery
170 MW storage in Mercer, NJ · In queue since September 2019 · Proposed COD August 2027
170 MW
Capacity
1
Components
Battery
6y 10m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-08-11
Interconnection Agreement executed with PJM per queue filing
The Lamberton Road Battery project is a proposed 170 MW battery storage project located in Mercer County, New Jersey. The project is being developed within the PJM Interconnection queue as project AF1-237, with a queue entry date of September 28, 2019. The proposed commercial operation date is August 11, 2027. The project has an executed Interconnection Agreement (IA).
The project is interconnected to the PSEG utility grid at the Mercer 230 kV point of interconnection. The Lamberton Road Battery project has appeared in recent news coverage regarding energy storage development in the PJM region.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Mercer
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
NRIS
Point of Interconnection
Mercer 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MERCER 13 KV WHNUG
- POI Substation
- Mercer Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Lamberton Road BatteryForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.