Hoosier Line Solar
180 MW generation in White, IN · In queue since September 2019 · Proposed COD September 2027
180 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-15
Interconnection Agreement executed per LBNL queue status
The Hoosier Line Solar project is a proposed 180 MW solar generation facility in White County, Indiana. The project, under development in the PJM Interconnection queue as entry PJM-AF1-207, was initially entered into the queue on September 27, 2019, with a proposed commercial operation date of September 15, 2027. The interconnection utility is AEP, and the project's point of interconnection is the Reynolds-Olive #1 345 kV line. Its interconnection status is currently in the Facility Study phase.
The Hoosier Line Solar project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Reynolds-Olive #1 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Hoosier Line SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.