Jackson Center Solar II
20 MW generation in Mercer, PA · In queue since August 2019 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Jackson Center Solar II project is a proposed 20 MW solar generation project located in Mercer County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-093, with a queue entry date of August 31, 2019, and a proposed commercial operation date of July 31, 2026. The interconnecting utility is ATSI.
The project's interconnection agreement has been executed. It has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Mercer
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Henderson-Stoneboro 69 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Jackson Center Solar IIForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.