Flat Run Solar
55 MW generation in Barren, KY · In queue since August 2019 · Proposed COD December 2026
55 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-15
Flat Run Solar is a proposed 55 MW solar generation project located in Barren County, Kentucky. The project is in the PJM interconnection queue as entry PJM-AF1-083, with a queue entry date of August 31, 2019, and a proposed commercial operation date of December 15, 2026. The interconnection agreement has been executed. The designated point of interconnection is the Green County-Saloma 161 kV line.
The Flat Run Solar project is being developed within the East Kentucky Power Cooperative (EKPC) service area. Recent news coverage indicates activity related to the project in the industry, deals, and regulatory sectors.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Barren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Green County-Saloma 161 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.