Dover Solar
20 MW generation in York, PA · In queue since July 2019 · Proposed COD September 2027
20 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-07
Dover Solar is a proposed 20 MW solar generation project located in York County, Pennsylvania. The project is listed in the PJM interconnection queue as entry PJM-AF1-057, with a queue entry date of July 31, 2019. The proposed commercial operation date is October 14, 2026, and the project's interconnection agreement has been executed.
The Dover Solar project is being developed within the PJM service territory. The point of interconnection is the Jackson-Three Mile Island 230 kV II line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
NRIS
Point of Interconnection
Jackson-Three Mile Island 230 kV II
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Dover SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.