Plano Skies Energy Center
100 MW generation in Kendall, IL · In queue since May 2019 · Proposed COD May 2030
100 MW
Capacity
1
Components
Solar
7y 6m
In Queue
System Impact Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11 years
Study Phase
TC1
Interconnection request submitted to ISO/RTO
EP; FINAL AGREEMENT; TC1
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-30
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Original proposed COD per PJM queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2022. No independent news or research sources found to validate or update this target, which is now 2+ years past.
Developer: Only the LBNL filing entity is known. No press releases, corporate announcements, or news coverage found to identify a parent operating company or confirm if this is a project-specific LLC.
Status: LBNL shows Active status at System Impact Study phase. Absence of any news coverage, financing announcements, or construction updates suggests project may be stalled or proceeding quietly.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed PJM-AF1-030 project is a 100 MW solar generation facility located in Kendall County, Illinois. Interconnection is with ComEd within the PJM Interconnection queue. The project entered the queue on May 17, 2019, and has a proposed commercial operation date of December 1, 2022. Its interconnection status is currently in the System Impact Study phase.
The project consists of 100 MW of solar photovoltaic generation. The point of interconnection is the Sandwich-Plano 138 kV line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Kendall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Plano Skies Energy Center, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Sandwich-Plano 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Illinois Solar in Illinois growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.