Prospect Power
200 MW storage in Rockingham, VA · In queue since May 2019 · Proposed COD May 2026
200 MW
Capacity
1
Components
Battery
7y 6m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7 years
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Partially in Service - Under Construction
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
- 2026-01·Swift Current Energy→Elevate Renewablesbusinesswire.com
Milestones in this assessment
Interconnection Agreement executed with PJM (queue date 2019-05-13)
businesswire.comElevate Renewables acquires 150 MW Prospect Power Storage project from Swift Current Energy
businesswire.comTarget commercial operation date per LBNL queue; construction phase confirmed Jan 2026
businesswire.comResearch sources and reasoning (1 recorded sources)
high confidence at research time
Commercial operation date: LBNL queue shows 2026-05-31 COD. News extraction from Jan 2026 indicates project is in construction phase, consistent with this timeline, but no independent COD confirmation found in research.
Developer: Business Wire press release (Jan 15, 2026) confirms Elevate Renewables acquired the project from Swift Current Energy. Current owner is Elevate; Swift Current was the original developer.
Status: LBNL shows IA Executed status. News extraction confirms construction underway as of Jan 2026, indicating active development post-interconnection agreement.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Prospect Power is a proposed 200 MW battery storage project located in Rockingham County, Virginia. The project is being developed within the PJM Interconnection queue under queue ID PJM-AF1-028. Its queue entry date is May 13, 2019, and the proposed commercial operation date is February 1, 2026. The interconnection agreement for Prospect Power has been executed.
The project is interconnected to the Dominion utility grid at the Endless Caverns 115 kV point of interconnection. Prospect Power has been the subject of recent news coverage, with eight articles focusing on deals, regulatory matters, and development aspects of the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Rockingham
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Endless Caverns 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- pending
- POI Substation
- Endless Caverns Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26