Welcome Solar III, LLC
17.9 MW hybrid in Crawford, PA · In queue since April 2019 · Proposed COD August 2026
17.9 MW
Capacity
1
Components
Solar
7y 7m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 4m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Partially in Service - Under Construction
Project under construction
Typical: 18–30 months
Proposed COD: 2026-08-29
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Welcome Solar III, LLC is a proposed 17.9 MW hybrid solar and battery project located in Crawford County, Pennsylvania. The development project, under the queue ID PJM-AE2-343, is interconnected within the PJM Interconnection queue. The project entered the queue on April 1, 2019, and has a proposed commercial operation date of August 29, 2026. The interconnection agreement (IA) for the project has been executed.
The project consists of 17.9 MW of solar generation capacity. The designated point of interconnection (POI) is the Andover (Maysville) 69 kV II substation. The utility is ATSI, and the entity is PJM. The project's status is currently listed as active.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
NRIS
Point of Interconnection
Andover (Maysville) 69 kV II
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
WED Shun III, LLC
Data-driven briefing on Welcome Solar III, LLC — fleet, generation, financial, and news signals.
SMUD at Van Conett
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Welcome Solar III, LLC
Data-driven briefing on Welcome Solar III, LLC — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.