PJM-AE2-341
150 MW generation in Kendall, IL · In queue since March 2019 · Proposed COD December 2022
150 MW
Capacity
1
Components
Solar
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 9m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AE2-341 is a proposed solar generation project with a total capacity of 150 MW, located in Kendall County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2019. Its proposed commercial operation date is December 1, 2022. The project is currently in the System Impact Study phase of the interconnection process.
The proposed project is located within the ComEd utility territory and connects to the Sandwich-Plano 138 kV point of interconnection. The project consists of 150 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
IL
County
Kendall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Sandwich-Plano 138 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AE2-341Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.