Grassy Plains
40 MW generation in Fayette, KY · In queue since March 2019 · Proposed COD June 2027
40 MW
Capacity
1
Components
Solar
7y 4m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-06-30
The Grassy Plains project is a proposed 40 MW solar generation facility in Fayette County, Kentucky. The project is being developed within the PJM Interconnection queue as project number PJM-AE2-339. The project entered the queue on March 31, 2019, and has a proposed commercial operation date of June 30, 2027.
The project has an Interconnection Agreement (IA) that has been executed. The designated point of interconnection (POI) for the project is the Avon 138 kV substation. The transmission utility is EKPC.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Avon 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AVONLAK2138 KV 800_B
- POI Substation
- Avon Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Grassy PlainsForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.