Elkhart County Solar Project (PJM-AE2-323) — Project Summary

Queue ID
PJM-AE2-323
Capacity
100 MW
Technology
Solar
Status
active
Location
Elkhart, IN
Region
PJM
Developer
IA Status
IA Executed

Elkhart County Solar Project

PJM-AE2-323BetaActiveSolarPJMLBNL + Live

100 MW generation in Elkhart, IN · In queue since March 2019 · Proposed COD May 2026

BA: MISOISO/RTO: PJMNERC: RFCRC: MISO

100 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2026

Status
Latest milestoneCOD achievedInside INdiana Business · 2025-11-17
Expected CODQ2 2025Inside INdiana Business · 2024-05-20
Interconnection

Total Duration

7y 2m

Schedule

1 months past proposed COD

Construction75%
Queue EntryMar 30, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-05-01

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

The Elkhart County Solar Project is a proposed 100 MW solar generation project located in Elkhart County, Indiana. The project is listed in the PJM interconnection queue as entry AE2-323, with a queue entry date of March 30, 2019, and a proposed commercial operation date of May 1, 2026. The interconnection agreement (IA) has been executed.

The project is linked to the existing Elkhart County Solar Project (EIA plant ID 66647). The Elkhart County Solar Project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

IN

County

Elkhart

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Twin Branch-Guardian 138 kV

Data Source

LBNL + Live

DeveloperLightsource bp±Inside INdiana Business · 2024-10-18
EPC contractorInovateus Solar LLC±Inside INdiana Business · 2024-10-18
AgencyElkhart County CommissionersElkhart County · 2022-01-17
RulingDenialElkhart County · 2022-01-17
Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
N ILLINOIS HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
MCNUTT 34.5 KV ELKHARSP
POI Substation
AEP Guardian Station

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (4)Beta

Last updated 2026-03-26

View all articles

No Ask reports yet for this entity.

Ask about Elkhart County Solar Project
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.