Blue Rock Solar
100 MW generation in Buckingham, VA · In queue since March 2019 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Engineering and Procurement
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Buckingham County Board of Supervisors approved Blue Rock Solar project
farmvilleherald.comResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: LBNL queue shows 2026-12-31 COD. No contradicting or confirming signals from news/research; local approval in Nov 2023 is consistent with 2026 timeline but doesn't provide alternate date.
Developer: LBNL developer field is null. News identifies 'Blue Rock Solar LLC' as applicant to Buckingham County, which appears to be a project-specific LLC. No parent/operating company identified in available sources.
Status: LBNL shows 'active' with IA Executed status. Buckingham County Board of Supervisors approved the project in November 2023, indicating active permitting progress consistent with queue status.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Blue Rock Solar is a proposed 100 MW solar generation project located in Buckingham County, Virginia. The project is being developed within the Dominion service area and has an interconnection agreement executed. It is listed in the PJM interconnection queue as entry AE2-259, with a queue entry date of March 28, 2019, and a proposed commercial operation date of December 31, 2026.
The Blue Rock Solar project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Buckingham
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Curdsville-Willis Mtn 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26