Pleasant Prairie Solar Energy Center
200 MW generation in Franklin, OH · In queue since March 2019 · Proposed COD December 2027
200 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Under Construction
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-30
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Construction kickoff with Blattner as EPC contractor
solarpowerworldonline.comExpected commercial operation Q1 2027
solarpowerworldonline.comResearch sources and reasoning (2 recorded sources)
high confidence at research time
- solarpowerworldonline.com/2025/06/invenergy-kicks-off-construction-on-240-mw-ohio-solar-project/
- dispatch.com/story/news/2020/12/12/inevergy-proposes-250-megawatt-solar-farm-western-franklin-county/6484053002/
Commercial operation date: LBNL proposed COD of 2027-03-30 aligns with news-extracted Q1 2027 target from Solar Power World article covering construction start in June 2024.
Developer: LBNL snapshot has null developer field. News extraction identifies Invenergy as developer with 0.8 confidence across 2 supporting articles including Solar Power World and Columbus Dispatch.
Status: LBNL shows 'active' with IA Executed status. News confirms construction started June 10, 2024 per Solar Power World, advancing project beyond queue-active to active construction phase.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Pleasant Prairie Solar Energy Center is a proposed 200 MW solar generation project in Franklin County, Ohio. The project, developed by AEP, is currently active in the PJM interconnection queue as entry AE2-214, with a queue entry date of March 23, 2019. The proposed commercial operation date is March 30, 2027, and the Interconnection Agreement (IA) has been executed.
The Pleasant Prairie Solar Energy Center has been the subject of recent news coverage, with five articles categorized as industry and development related.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Cole 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- COLE 34.5 KV PLEPRASP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesPrairie
Data-driven briefing on Prairie — fleet, generation, financial, and news signals.
Prairie Solar (VA)
Data-driven briefing on Prairie Solar — fleet, generation, financial, and news signals.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Pleasant Prairie Solar Energy Center
Data-driven briefing on Pleasant Prairie Solar Energy Center — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.