Bradford Solar
100.5 MW generation in Mckean, PA · In queue since March 2019 · Proposed COD December 2027
100.5 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-12-15
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2027. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL filing shows no developer entity. Live search returned no results identifying the project sponsor, operating company, or filing LLC.
Status: LBNL shows 'Active' status with executed interconnection agreement. No news coverage found to provide ground-truth updates on permitting, financing, or construction progress.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bradford Solar is a proposed 100.5 MW solar generation development project located in McKean County, Pennsylvania. The project is listed in the PJM Interconnection queue under queue ID PJM-AE2-139. Its proposed point of interconnection is the East Towanda-Grover 230 kV line within the service territory of PENELEC (Pennsylvania Electric Company). The project requested Network Integration Resource Interconnection Service (NRIS). No developer is identified in the available queue data.
Bradford Solar entered the PJM interconnection queue on March 9, 2019. It has reached an executed interconnection agreement (IA Executed), but its current queue status is listed as suspended. The project's proposed commercial operation date is December 15, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Mckean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
East Towanda-Grover 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Radford
Data-driven briefing on Radford — fleet, generation, financial, and news signals.
SMUD at Van Conett
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Bradford Solar PA
Data-driven briefing on Bradford Solar — fleet, generation, financial, and news signals.
Ord
Data-driven briefing on Ord — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.