Bradford Solar (PJM-AE2-139) — Project Summary

Queue ID
PJM-AE2-139
Capacity
100.5 MW
Technology
Solar
Status
active
Location
Mckean, PA
Region
PJM
Developer
IA Status
IA Executed

Bradford Solar

PJM-AE2-139BetaActiveSolarPJMLBNL + Live

100.5 MW generation in Mckean, PA · In queue since March 2019 · Proposed COD December 2027

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

100.5 MW

Capacity

1

Components

Solar

7y 4m

In Queue

IA Executed

IA Phase

COD target: 2027

Interconnection

Total Duration

8y 9m

Construction75%
Queue EntryMar 9, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-15

Cross-source intelligence
Beta
Low confidence·0 sources·as of 2026-06-01
Expected COD
2027-12-15
From queue filing
Developer
Status
Active
Active — IA Executed as of queue filing, no public updates on construction timeline
Financing
Unannounced
Key milestones
IA executedMost recent

Interconnection Agreement executed per LBNL queue status

About

The proposed Bradford Solar project is a 100.5 MW solar generation facility located in McKean County, Pennsylvania. The project is in the PJM interconnection queue as entry AE2-139, with a queue entry date of March 9, 2019, and a proposed commercial operation date of December 15, 2027. The interconnecting utility is PENELEC. The project's interconnection agreement has been executed.

The Bradford Solar project has been mentioned in recent industry news.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

PA

County

Mckean

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PENELEC

Entity

PJM

Service Type

NRIS

Point of Interconnection

East Towanda-Grover 230 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Bradford Solar
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.