Cassius Blue Solar
300 MW hybrid in Sussex, VA · In queue since February 2019 · Proposed COD August 2031
300 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Phase
COD target: 2031
Total Duration
12y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2031-08-01
Interconnection Agreement executed per LBNL queue status
The Cassius Blue Solar project is a proposed 300 MW hybrid solar and battery energy storage development in Sussex County, Virginia. The project consists of 300 MW of solar generation capacity. It is located within the PJM Interconnection region and is interconnected to the Carson-Rogers Road 500 kV substation.
The project, assigned queue ID PJM-AE2-094, entered the PJM interconnection queue on February 26, 2019, with a proposed commercial operation date of August 1, 2031. The interconnection agreement (IA) for the project has been executed. The interconnecting utility is Dominion.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Carson-Rogers Road 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cassius Blue SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.