Potter Solar
35 MW generation in Potter, PA · In queue since February 2019 · Proposed COD July 2026
35 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-31
Potter Solar is a proposed 35 MW solar generation project located in Potter County, Pennsylvania. The project is interconnected within the PJM Interconnection queue as entry AE2-074, with a queue entry date of February 20, 2019. The proposed commercial operation date is July 31, 2026. The project's interconnection status is currently in the System Impact Study phase.
The development is linked to an existing operating plant named Potter Solar (EIA plant ID 67876). The confidence level of the match between the queue project and the existing plant is 85%. The designated point of interconnection (POI) is the Potter 46 kV substation.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Potter
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
NRIS
Point of Interconnection
Potter 46 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- APS
- POI Substation
- Potter Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Potter SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.