Eastern Cottontail Solar (PJM-AE2-048) — Project Summary

Queue ID
PJM-AE2-048
Capacity
220 MW
Technology
Solar
Status
active
Location
Fairfield, OH
Region
PJM
Developer
—
IA Status
IA Executed

Eastern Cottontail Solar

PJM-AE2-048BetaActiveSolarPJMLBNL + Live

220 MW generation in Fairfield, OH · In queue since January 2019 · Proposed COD December 2028

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

220 MW

Capacity

1

Components

Solar

7y 10m

In Queue

IA Executed

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

9y 11m

Construction75%
Queue EntryJan 31, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Engineering and Procurement

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-12-31

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 31, 2028
From queue filing
Developer in saved assessment
EDF Renewables
From queue filing
Status at research time
Active
Active — Ohio Power Siting Board approval received, IA executed, pre-construction phase
Financing
Not recorded

Milestones in this assessment

IA executedAug 22, 2025

Interconnection Agreement executed with PJM

sciotopost.com
Permit approvedAug 22, 2025Latest in this assessment

Ohio Power Siting Board granted approval for 220 MW solar project in Fairfield County

sciotopost.com
Research sources and reasoning (2 recorded sources)

medium confidence at research time

  1. sciotopost.com/eastern-cottontail-solar-project-approved-in-fairfield-county-by-siting-board/
  2. 10tv.com/article/news/local/boomtown-ohio/new-solar-farm-pleasantville-fairfield-county-debate-safety-property-values/530-a6cb1848-726c-4acd-89a7-3d290268821f

Commercial operation date: Only LBNL queue data provides a COD target of 2028-12-31. No news sources or press releases mention a specific commercial operation date, so LBNL remains the sole source despite potential staleness.

Developer: News sources identify 'EDF Power Solutions' as the applicant/developer. EDF Power Solutions is the development arm of EDF Renewables (formerly EDF Renewable Energy). LBNL queue snapshot has null developer field, so no shell-LLC vs parent comparison possible.

Status: LBNL shows 'active' status with IA executed. News confirms Ohio Power Siting Board approval granted (regulatory milestone achieved), consistent with active pre-construction status.

Project lifecycle
as of 2025-08-21
OperationalNoLancaster Eagle-Gazette · 2025-08-21
TechnologySolarLancaster Eagle-Gazette · 2025-08-21
Permit decisionGrantedLancaster Eagle-Gazette · 2025-08-21

About

Saved background

Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Eastern Cottontail Solar project is a proposed 220 MW solar generation facility in Fairfield County, Ohio. The project, developed under the utility AEP, is located within the PJM Interconnection region and entered the PJM queue as project AE2-048 on January 31, 2019. The proposed commercial operation date is December 31, 2028, and the project has an Interconnection Agreement (IA) executed.

The Eastern Cottontail Solar project has been the subject of recent news coverage, with three articles categorized as regulatory matters.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • PJM queue source as of: Oct 25, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

OH

County

Fairfield

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

—

Utility

AEP

Entity

PJM

Service Type

NRIS

Point of Interconnection

Muskingum-W. Millersport 345 kV

Data Source

LBNL + Live

AgencyOhio Power Siting Board10tv.com · 2025-09-11
RulingApproval10tv.com · 2025-09-11
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.