Raleigh Solar Project
90 MW generation in Raleigh, WV · In queue since September 2018 · Proposed COD June 2025
90 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Phase
COD target: 2025
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2025-06-25
The proposed Raleigh Solar Project is a 90 MW solar generation project located in Raleigh County, West Virginia. The project is interconnected to the PJM Interconnection queue under queue ID PJM-AE1-212. Its queue entry date was September 10, 2018, and the proposed commercial operation date is June 25, 2025. The project's interconnection agreement has been executed, but its current status is listed as suspended.
The project is being developed within the American Electric Power (AEP) service territory. The point of interconnection is the Grandview-Clifftop 138 kV line. The Raleigh Solar Project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Raleigh
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Grandview-Clifftop 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Raleigh Solar ProjectForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.