Fountain Point Solar
206.55 MW generation in Union, OH · In queue since August 2018 · Proposed COD December 2021
206.55 MW
Capacity
1
Components
Solar
7y 9m
In Queue
System Impact Study
IA Phase
COD target: 2021
Total Duration
3y 4m
Schedule
54 months past proposed COD
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
PJM-AE1-092 is a proposed solar generation project with a total capacity of 206.6 MW. The project is located in Union County, Ohio, and interconnects to the PJM grid at the Blue Jacket-Kirby 138 kV point of interconnection. The project entered the PJM interconnection queue on August 31, 2018, with a proposed commercial operation date of December 31, 2021. Its interconnection status is currently in the System Impact Study phase.
The Dayton utility is associated with the project. The proposed project consists solely of solar generation, with no battery storage or other generation types included in the listed components.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Fountain Point Solar Energy LLC
Utility
Dayton
Entity
PJM
Service Type
NRIS
Point of Interconnection
Blue Jacket-Kirby 138 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Fountain Point SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.