Jackson Generation
120 MW generation in Will, IL · In queue since March 2018 · Proposed COD January 2027
120 MW
Capacity
1
Components
Gas
8y 4m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
8y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2027-01-01
- 2022-09·J-POWER USA Development Co. Ltd.→Gulf Energy Development Public Co.source
Jackson Generation is a proposed 120 MW natural gas generation project located in Will County, Illinois. The development project is interconnected to the ComEd utility network and participates in the PJM Interconnection queue as entry PJM-AD2-194, with a queue entry date of March 31, 2018. The project's proposed commercial operation date is January 1, 2027, and the Interconnection Agreement (IA) has been executed.
The Jackson Generation project has been the subject of recent news coverage, with 14 articles published across industry, regulatory, deals, grid, and development categories.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Will
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Elwood 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 929 JACK22 KV GEN1
- POI Substation
- Elwood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 6 articlesNo Ask reports yet for this entity.
Ask about Jackson GenerationForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.