Glen Falls Facility
45 MW generation in Harrison, WV · In queue since March 2018 · Proposed COD January 2029
45 MW
Capacity
1
Components
Gas
8y 8m
In Queue
IA Executed
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Under Construction
Project under construction
Typical: 24–48 months
Proposed COD: 2029-01-31
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed Glen Falls Facility is a 45 MW natural gas generation project located in Harrison County, West Virginia. The project is listed in the PJM interconnection queue as entry AD2-192, with a queue entry date of March 31, 2018. The proposed commercial operation date is January 31, 2029.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Glen Falls 138kV line. The queue data indicates the project is actively under development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Harrison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
NRIS
Point of Interconnection
Glen Falls 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Little Falls (WA)
Data-driven briefing on Glen Falls Facility — fleet, generation, financial, and news signals.
NASA Wallops Flight Facility Solar
Data-driven briefing on Glen Falls Facility — fleet, generation, financial, and news signals.
Glen
Data-driven briefing on Glen — fleet, generation, financial, and news signals.
Jarratt Energy Facility 2 queue pipeline — 1 projects by technology and status
Data-driven briefing on Glen Falls Facility — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.