Walnut Solar I (PJM-AD2-039) — Project Summary

Queue ID
PJM-AD2-039
Capacity
20 MW
Technology
Solar
Status
active
Location
King And Queen, VA
Region
PJM
Developer
—
IA Status
IA Executed

Walnut Solar I

PJM-AD2-039BetaActiveSolarPJMLBNL + Live

20 MW generation in King And Queen, VA · In queue since January 2018 · Proposed COD July 2026

BA: PJMISO/RTO: PJMNERC: SERCRC: PJM

20 MW

Capacity

1

Components

Solar

8y 10m

In Queue

IA Executed

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 6m

Schedule

4 months past proposed COD

Construction75%
Queue EntryJan 20, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Partially in Service - Under Construction

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-07-14

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Walnut Solar I is a proposed 20 MW solar generation project located in King and Queen County, Virginia. The development project is listed in the PJM Interconnection queue under queue ID PJM-AD2-039 and lies within the service territory of Dominion. The project consists of a single solar component with a capacity of 20 MW. It is proposed to connect to the grid at the Harmony Village-Shackleford 115 kV point of interconnection. It has requested Network Resource Interconnection Service (NRIS).

The project entered the PJM interconnection queue on January 20, 2018, and its queue status is currently listed as active. An interconnection agreement (IA) has been executed for the project, an advanced milestone in the PJM interconnection process. The proposed commercial operation date for Walnut Solar I is July 14, 2026.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • PJM queue source as of: Oct 25, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

VA

County

King And Queen

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

—

Utility

Dominion

Entity

PJM

Service Type

NRIS

Point of Interconnection

Harmony Village-Shackleford 115 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
POI Substation
HARMONY

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.