Osagrove Flats Wind
150 MW generation in Lasalle, IL · In queue since January 2018 · Proposed COD October 2026
150 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 9m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Partially in Service - Under Construction
Project under construction
Typical: 18–36 months
Proposed COD: 2026-10-30
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue data
Research sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: LBNL proposes 2026-10-30 COD. News extraction references Q4 2026 for a ComEd substation expansion project, but this appears to be infrastructure enabling multiple projects rather than Osagrove Flats specifically. No direct project-specific COD updates found.
Developer: LBNL has no developer listed. News extraction identifies 'ComEd' as developer, but the linked article describes ComEd's Wilton Center Substation expansion—transmission infrastructure serving a cluster of projects, not Osagrove Flats Wind itself. ComEd is the utility, not the wind project developer. No actual developer identified.
Status: LBNL shows 'active' status with IA Executed. News indicates the enabling transmission infrastructure (Wilton Center Substation) began design engineering in Sept 2023 with Q4 2026 target, suggesting project remains on track pending grid upgrades.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Osagrove Flats Wind project is a proposed 150 MW wind generation facility in Lasalle County, Illinois. The project is located within the ComEd service area and is interconnected to the PJM grid at the Powerton-Nevada 345 kV point of interconnection.
The project, identified as PJM-AD2-038 in the PJM interconnection queue, entered the queue on January 22, 2018, and has a proposed commercial operation date of October 30, 2026. The project's interconnection agreement has been executed. The Osagrove Flats Wind project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Lasalle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Powerton-Nevada 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- 918_DANA34.5 KV OSAGFLWF
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesOsagrove Flats Wind
Data-driven briefing on Osagrove Flats Wind — fleet, generation, financial, and news signals.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Grove
Data-driven briefing on Grove — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.