Kingwood Solar (PJM-AD1-140) — Project Summary

Queue ID
PJM-AD1-140
Capacity
175 MW
Technology
Solar
Status
active
Location
Greene, OH
Region
PJM
Developer
IA Status
IA Executed

Kingwood Solar

PJM-AD1-140BetaActiveSolarPJMLBNL + Live

175 MW generation in Greene, OH · In queue since September 2017 · Proposed COD September 2026

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

175 MW

Capacity

1

Components

Solar

8y 10m

In Queue

IA Executed

IA Phase

Signed Sep 2021

Interconnection

Queue → IA

4 years

IA → COD

5 years

Total Duration

4 years

Construction75%
Queue EntrySep 29, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection AgreementSep 17, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-09-30

Cross-source intelligence
Beta
High confidence·1 sources·as of 2026-06-01
Expected COD
Developer
Vesper Energy
From queue filing
Status
Cancelled
Active in PJM queue (IA executed 2021-09-17) but project denied by Ohio Power Siting Board in December 2022, effectively cancelling development
Financing
Cancelled
Key milestones
IA executedSep 17, 2021

Interconnection Agreement executed with PJM

source
WithdrawnDec 2022Most recent

Ohio Power Siting Board denied project application

source
Project lifecycle
as of 2022-12-20
OperationalNoFarm and Dairy · 2022-12-20
TechnologySolarFarm and Dairy · 2022-12-20
DeveloperVesper EnergyFarm and Dairy · 2022-12-20
Permit decisionDeniedFarm and Dairy · 2022-12-20
About

Kingwood Solar is a proposed 175 MW solar generation project located in Greene County, Ohio. The project is in the PJM interconnection queue as entry AD1-140, with a queue entry date of September 29, 2017, and a proposed commercial operation date of September 30, 2026. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Greene-Clark 138 kV line, and the utility is ATSI.

The project is linked to an existing operating plant of the same name (Kingwood Solar) with EIA plant ID 65425. The project has been the subject of recent news coverage, with eight articles categorized as industry and regulatory news.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

OH

County

Greene

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

ATSI

Entity

PJM

Service Type

NRIS

Point of Interconnection

Greene-Clark 138 kV

Data Source

LBNL + Live

ApplicantVesper EnergyFarm and Dairy · 2022-12-20
AgencyOhio Power Siting BoardFarm and Dairy · 2022-12-20
RulingDenialFarm and Dairy · 2022-12-20
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26