Short Mountain Wind Energy
80 MW generation in Hardy, WV · In queue since September 2017 · Proposed COD December 2027
80 MW
Capacity
1
Components
Wind
9y 2m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Proposed COD: 2027-12-31
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Short Mountain Wind Energy is a proposed 80 MW wind generation project located in Hardy County, West Virginia. The development project is listed in the PJM Interconnection queue under queue ID PJM-AD1-125, with APS as the associated transmission utility. The project would connect to the grid at the Baker 138 kV point of interconnection and has requested Network Resource Interconnection Service (NRIS).
The project entered the PJM queue on September 28, 2017, and has a proposed commercial operation date of December 31, 2027. An interconnection agreement has been executed for the project, although its current queue status is listed as suspended. Short Mountain Wind Energy has appeared in recent news coverage, with nine articles identified. Four concern development, four cover industry topics, and one addresses regulatory matters.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Hardy
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
NRIS
Point of Interconnection
Baker 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FOOTHILL18 KV UNIT 5
- POI Substation
- Baker Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26