Heritage Prairie Wind
850 MW generation in Kankakee, IL · In queue since September 2017 · Proposed COD December 2028
850 MW
Capacity
1
Components
Wind
9y 2m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Under Construction
Project under construction
Typical: 18–36 months
Proposed COD: 2028-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (7 recorded sources)
medium confidence at research time
- shawlocal.com/daily-journal/2026/05/30/26b-heritage-prairie-renewable-project-in-kankakee-and-livingston-counties-on-schedule/
- patternenergy.com/projects/heritage-prairie-wind/
- patternenergy.com/projects/heritage-prairie-renewable/
- heritageprairiewind-patternenergy.nationbuilder.com/
- villageofunionhill.org/wp-content/uploads/2023/11/Heritage_Prairie_Wind_Union_Hill_Presentation_2023Nov15.pdf
- gem.wiki/Heritage_Prairie_Wind
- cleanview.co/power-projects/planned/wind-farms/illinois/AD1-100/heritage-prairie-wind
Commercial operation date: Only the LBNL proposed COD of 2028-12-31 is available. Cleanview's 'expected to come online in December 2028' matches it but looks aggregator-derived, not independent. The Shaw Local headline says the project is 'on schedule' but gives no date in the snippet.
Developer: LBNL leaves the developer field blank, so there is nothing to compare. Pattern Energy's own project pages (Heritage Prairie Wind / Heritage Prairie Renewable) and its project-specific community site identify it as the developer. The Pattern–Cordelio acquisition result is unrelated to this project.
Status: LBNL shows active with an executed IA. Global Energy Monitor lists the project as pre-construction and Shaw Local (2026) reports it on schedule. Nothing indicates withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AD1-100 is a proposed wind generation project with a total capacity of 850 MW, located in Ford County, Illinois. The project is interconnected to the ComEd utility within the PJM Interconnection queue. The queue entry date is September 22, 2017, and the proposed commercial operation date is December 31, 2028.
The project's interconnection agreement has been executed. The point of interconnection is at the Loretto-Wilton 345 kV and Braidwood-Davis Creek 345 kV lines.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.