Rochelle Solar
40 MW generation in Ogle, IL · In queue since April 2017 · Proposed COD May 2028
40 MW
Capacity
1
Components
Solar
9y 3m
In Queue
IA Executed
IA Phase
COD target: 2028
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-27
The Rochelle Solar project is a proposed 40 MW solar generation project located in Ogle County, Illinois. The project is in the PJM interconnection queue as entry AD1-013, with a queue entry date of April 6, 2017, and a proposed commercial operation date of May 27, 2028. The interconnecting utility is ComEd.
The project's interconnection agreement has been executed. The point of interconnection is the Twombly Road 138kV substation. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Ogle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Twombly Road 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Rochelle SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.