Cedar Creek Solar
20 MW generation in Kent, DE · In queue since April 2017 · Proposed COD May 2027
20 MW
Capacity
1
Components
Solar
9y 3m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-05-30
Cedar Creek Solar is a proposed 20 MW solar generation project located in Kent County, Delaware. The project is interconnected to the PJM grid via the Cedar Creek 138kV I point of interconnection, and is in the PJM interconnection queue as entry AC2-184, filed on April 1, 2017. The proposed commercial operation date is May 30, 2027, and the interconnection agreement has been executed. The project's status is currently listed as suspended.
The project is being developed within the Delmarva Power & Light (DPL) service area. Recent news coverage has discussed the project's potential impact on the local energy landscape.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
DE
County
Kent
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
NRIS
Point of Interconnection
Cedar Creek 138kV I
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CEDARCRE34.5 KV CEDARSP
- POI Substation
- Cedar Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cedar Creek SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.