Walnut Solar I
20 MW generation in King And Queen, VA · In queue since March 2017 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
9y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-07-14
Walnut Solar I is a proposed solar generation project with a total capacity of 20 MW, located in King And Queen County, Virginia. The project is being developed within the Dominion service area and has appeared in recent news coverage. It is listed in the PJM interconnection queue as entry PJM-AC2-110, with a queue entry date of March 14, 2017, and a proposed commercial operation date of July 14, 2026.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Harmony Village-Shackleford 115kV substation.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
King And Queen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Harmony Village-Shackleford 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- HARMONY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Walnut Solar IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.