Eaton OH Solar
49.9 MW generation in Preble, OH · In queue since February 2017 · Proposed COD January 2027
49.9 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Phase
Signed Jun 2019
Queue → IA
2y 4m
IA → COD
7y 7m
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-28
The Eaton OH Solar project is a proposed 49.9 MW solar generation project located in Preble County, Ohio. The project is listed in the PJM interconnection queue as entry PJM-AC2-067, with a queue entry date of February 27, 2017. The proposed commercial operation date is January 28, 2027.
The interconnection agreement for the Eaton OH Solar project has been executed. The project is interconnected to the Dayton utility grid at the Camden-Crystal I 69kV point of interconnection.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Preble
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
NRIS
Point of Interconnection
Camden-Crystal I 69kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Eaton OH SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.