Sycamore Creek Solar (PJM-AC2-015) — Project Summary

Queue ID
PJM-AC2-015
Capacity
117 MW
Technology
Solar
Status
active
Location
Crawford, OH
Region
PJM
Developer
IA Status
IA Executed

Sycamore Creek Solar

PJM-AC2-015BetaActiveSolarPJMLBNL + Live

117 MW generation in Crawford, OH · In queue since December 2016 · Proposed COD December 2025

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

117 MW

Capacity

1

Components

Solar

9y 7m

In Queue

IA Executed

IA Phase

COD target: 2025

Interconnection

Total Duration

9 years

Schedule

7 months past proposed COD

Construction75%
Queue EntryDec 29, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-12-16

Cross-source intelligence
Beta
Low confidence·2 sources·as of 2026-06-01
Expected COD
2025-12-16
From queue filing
Developer
Status
Active
Active — IA Executed, Amazon PPA secured, not yet operational as of September 2024
Financing
Secured
Amazon PPA announced November 2023 as part of 3-project Ohio solar investment package
Key milestones
IA executedDec 29, 2016

Interconnection Agreement executed with PJM (queue date)

source
Financing closeNov 2023Most recent

Amazon announced PPA for Sycamore Creek Solar as part of Ohio solar portfolio

source
Project lifecycle
as of 2024-09-08
OperationalNoBucyrus Telegraph-Forum · 2024-09-08
TechnologySolarBucyrus Telegraph-Forum · 2024-09-08
About

The Sycamore Creek Solar project is a proposed 117 MW solar generation facility located in Crawford County, Ohio. The project is in the PJM interconnection queue as entry PJM-AC2-015, with a queue entry date of December 29, 2016. The proposed commercial operation date is December 16, 2025, and the Interconnection Agreement (IA) has been executed. The interconnecting utility is AEP.

The Sycamore Creek Solar project has been the subject of recent news coverage, with 10 articles appearing in industry publications. News categories include industry, grid, regulatory, deals and development.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

OH

County

Crawford

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

NRIS

Point of Interconnection

Chatfield-Howard 138kV

Data Source

LBNL + Live

OfftakerAmazonThe Columbus Dispatch · 2023-11-15
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-26

View all articles

No Ask reports yet for this entity.

Ask about Sycamore Creek Solar
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.