Springfield Solar
80 MW generation in Hanover, VA · In queue since October 2016 · Proposed COD March 2027
80 MW
Capacity
1
Components
Solar
9y 9m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
10y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-31
The Springfield Solar project is a proposed 80 MW solar generation project located in Hanover County, Virginia. The project is being developed within the Dominion service area and has an interconnection queue entry date of October 31, 2016, in the PJM Interconnection queue (queue ID PJM-AC1-191). The proposed commercial operation date is March 31, 2027.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Elmont 115kV substation. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Hanover
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Elmont 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MTNROAD 35 KV HENRICLF
- POI Substation
- Elmont Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Springfield SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.