Edgecome Solar Energy Center
75 MW generation in Edgecombe, NC · In queue since August 2016 · Proposed COD December 2025
75 MW
Capacity
1
Components
Solar
9y 11m
In Queue
IA Executed
IA Phase
Signed Sep 2020
Queue → IA
4y 1m
IA → COD
5y 3m
Total Duration
4y 1m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-31
The Edgecome Solar Energy Center is a proposed 75 MW solar generation project located in Edgecombe County, North Carolina. The project is being developed within the Dominion service area and has interconnection queue ID PJM-AC1-034 in the PJM Interconnection queue. Its queue entry date is August 11, 2016, and the proposed commercial operation date is December 31, 2025. The project's interconnection agreement has been executed.
The Edgecome Solar Energy Center has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Edgecombe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Heartsease DP - Mayo Dunbar 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Edgecome Solar Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.