Bergen Generating Station
51.1 MW generation in Bergen, NJ · In queue since April 2016 · Proposed COD June 2027
51.1 MW
Capacity
1
Components
Gas
10y 3m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
11y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2027-06-01
The Bergen Generating Station is a proposed 51.1 MW gas-fired generation project located in Bergen County, New Jersey. The project, developed by PSEG, is in the PJM interconnection queue as entry AB2-092, with a queue entry date of January 1, 1970. Its proposed commercial operation date is June 1, 2027, and the project has an Interconnection Agreement (IA) executed.
The Bergen Generating Station has been the subject of recent news coverage, with 23 articles appearing in the press. These articles primarily focus on industry-related topics, with some discussion of regulatory and grid-related aspects.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Bergen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
NRIS
Point of Interconnection
Bergen 138kV
Data Source
LBNL + Live
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HCS 500 KV NYPUMP
- POI Substation
- North Bergen Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26