Mountaineer #1
36 MW generation in WV · In queue since October 2015 · Proposed COD June 2021
36 MW
Capacity
1
Components
Coal
10y 9m
In Queue
IA Executed
IA Phase
COD target: 2021
Total Duration
5y 8m
Schedule
62 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2021-06-01
The Mountaineer #1 project is a proposed 36 MW coal-fired generation project located in West Virginia. The developer is AEP. It is listed in the PJM interconnection queue as entry PJM-AB1-109, with a queue entry date of January 1, 1970. The proposed commercial operation date was June 1, 2021, and the project has an executed Interconnection Agreement (IA).
The project's point of interconnection (POI) is at the existing Mountaineer facility.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Mountaineer
Data Source
LBNL + Live
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MOUNTAIN26 KV MT1
- POI Substation
- Mountaineer Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Mountaineer #1Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.