PGE-23-239
200 MW storage in Multnomah, OR · In queue since December 2023 · Proposed COD December 2028
200 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Cluster Study
IA Phase
COD target: 2028
Total Duration
5 years
Study Phase
Portland
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PGE-23-239 is a proposed 200 MW battery storage project located in Multnomah County, Oregon. The project is in the Portland General Electric (PGE) interconnection queue, with an entry date of December 15, 2023, and a proposed commercial operation date of December 31, 2028. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, under development by PGE, consists entirely of battery storage. It is located in the West region and intends to interconnect at the Rivergate Substation 230kV.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Multnomah
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
NRIS
Point of Interconnection
Rivergate Substation 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PGE-23-239Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.