PGE-23-226
250 MW generation in Jefferson, OR · In queue since March 2023 · Proposed COD September 2027
250 MW
Capacity
1
Components
Wind
3y 4m
In Queue
Cluster Study
IA Phase
COD target: 2027
Total Duration
4y 6m
Study Phase
Central OR
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
PGE-23-226 is a proposed 250 MW wind generation project located in Jefferson County, Oregon. The project is listed in the Portland General Electric interconnection queue with an entry date of March 3, 2023. Its proposed commercial operation date is September 1, 2027.
The interconnection agreement for PGE-23-226 is currently listed as "In Progress (unknown study)". The point of interconnection is the Mountain View Substation 500KV. The project has appeared in recent news coverage regarding renewable energy development in the West region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
NRIS
Point of Interconnection
Mountain View Substation 500KV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PGE-23-226Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.