PGE-11-042
37 MW generation in Jefferson, OR · In queue since June 2011 · Proposed COD October 2013
37 MW
Capacity
1
Components
Other
15y 1m
In Queue
—
IA Status
COD target: 2013
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2013-10-01
PGE-11-042 is a proposed 37 MW generation project located in Jefferson County, Oregon. The project, which utilizes an unspecified "Other" technology, is interconnected with Portland General Electric (PGE). It entered the PGE interconnection queue on June 8, 2011, with a proposed commercial operation date of October 1, 2013.
The project's interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "Suspended." The point of interconnection (POI) is the Round Butte Substation at 230 kV.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
NRIS
Point of Interconnection
Round Butte Substation @ 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PGE-11-042Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.