PGE-10-036
400 MW generation in Sherman, OR · In queue since March 2010 · Proposed COD December 2014
400 MW
Capacity
1
Components
Wind
16y 4m
In Queue
—
IA Status
COD target: 2014
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2014-12-01
PGE-10-036 is a proposed 400 MW wind generation project located in Sherman County, Oregon. The project, under development by Portland General Electric (PGE), entered the Portland General Electric interconnection queue on March 23, 2010, with a proposed commercial operation date of December 1, 2014. The point of interconnection is the proposed Mikkalo Substation at 500 kV.
Currently, the project's interconnection status is listed as "suspended," and its interconnection agreement (IA) status is also "suspended."
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
NRIS/ERIS
Point of Interconnection
Proposed Mikkalo Substation @ 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PGE-10-036Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.