PacifiCorp-TCS-53
20 MW generation in Crook, OR · In queue since April 2020 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Phase
Signed Oct 2023
Queue → IA
3y 6m
IA → COD
3y 2m
Total Duration
3y 6m
Study Phase
Transition Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-01
PacifiCorp-TCS-53 is a proposed 20 MW solar generation project located in Crook County, Oregon. The developer is Get Along Solar XI LLC. The project consists of 20 MW of solar photovoltaic generation.
The project is in the PacifiCorp interconnection queue as of April 6, 2020, with a proposed commercial operation date of May 1, 2023. The interconnection agreement has been executed. The point of interconnection is the Ponderosa substation.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Get Along Solar XI LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Ponderosa substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-TCS-53Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.