Project PacifiCorp-TCS-52 — Project Summary

Queue ID
PacifiCorp-TCS-52
Capacity
20 MW
Technology
Solar
Status
active
Location
Crook, OR
Region
West
Developer
Get Along Solar II LLC
IA Status
IA Executed

PacifiCorp-TCS-52

PacifiCorp-TCS-52BetaActiveSolarPacifiCorpLBNL

20 MW generation in Crook, OR · In queue since April 2020 · Proposed COD November 2026

BA: BPATNERC: WECCRC: RCW

20 MW

Capacity

1

Components

Solar

6y 3m

In Queue

IA Executed

IA Phase

Signed Oct 2023

Interconnection

Queue → IA

3y 6m

IA → COD

3y 1m

Total Duration

3y 6m

Study Phase

Transition Cluster

Construction75%
Queue EntryApr 6, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementOct 10, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-11-01

About

PacifiCorp-TCS-52 is a proposed 20 MW solar generation project located in Crook County, Oregon. The project, developed by Get Along Solar II LLC, entered the PacifiCorp transmission queue on April 6, 2020, with a proposed commercial operation date of May 1, 2023. The point of interconnection is the Baldwin Road-Ponderosa transmission line. The project's interconnection agreement has been executed.

The proposed project consists of 20 MW of solar photovoltaic generation. It is currently listed as active in the PacifiCorp interconnection queue.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

OR

County

Crook

Grid Region

Mountain West

Market

Developer

Get Along Solar II LLC

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

NRIS

Point of Interconnection

Baldwin Road-Ponderosa transmission line

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project PacifiCorp-TCS-52
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.