PacifiCorp-TCS-09
300 MW hybrid in Utah, UT · In queue since November 2017 · Proposed COD November 2023
300 MW
Capacity
1
Components
Solar
8y 8m
In Queue
Suspended
IA Phase
Signed Jul 2023
Queue → IA
5y 8m
IA → COD
4 months
Total Duration
5y 8m
Study Phase
Transition Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2023-11-30
PacifiCorp-TCS-09 is a proposed 300 MW hybrid solar and battery project located in Utah County, Utah. The development project, proposed by Longroad Development Company, LLC, consists of 300 MW of solar capacity. It is interconnected to PacifiCorp via the Camp Williams-Mona #1 line.
The project entered the PacifiCorp Transmission Customer Service queue on November 30, 2017, with a proposed commercial operation date of November 30, 2023. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
Longroad Development Company, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Camp Williams-Mona #1 line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-TCS-09Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.