Project PacifiCorp-S0015 — Project Summary

Queue ID
PacifiCorp-S0015
Capacity
100 MW
Technology
Battery
Status
active
Location
Emery, UT
Region
West
Developer
IA Status
In Progress (unknown study)

PacifiCorp-S0015

PacifiCorp-S0015BetaActiveBatteryPacifiCorpLBNL

100 MW storage in Emery, UT · In queue since November 2022 · Proposed COD December 2026

BA: PACENERC: WECCRC: RCW

100 MW

Capacity

1

Components

Battery

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

4y 1m

In Study38%
Queue EntryNov 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

PacifiCorp-S0015 is a proposed 100 MW battery storage project located in Emery County, Utah. The project, being developed by PacifiCorp, entered the PacifiCorp interconnection queue on November 18, 2022, with a proposed commercial operation date of December 31, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".

The project consists of a single 100 MW battery component. The point of interconnection is the Emery substation.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Emery

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Emery substation

Data Source

LBNL

Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.