PacifiCorp-S0013
80 MW storage in Iron, UT · In queue since March 2022 · Proposed COD October 2025
80 MW
Capacity
1
Components
Battery
4y 4m
In Queue
IA Executed
IA Phase
COD target: 2025
Total Duration
3y 7m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-10-03
PacifiCorp-S0013 is a proposed 80 MW battery storage project located in Iron County, Utah. The project, developed by Iron Springs BESS LLC, entered the PacifiCorp interconnection queue on March 23, 2022, with a proposed commercial operation date of August 30, 2024. The point of interconnection is the Three Peaks substation.
The project's interconnection status is listed as "In Progress (unknown study)". It consists of a single 80 MW battery component. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
Iron Springs BESS LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Three Peaks substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-S0013Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.