PacifiCorp-S0009
80 MW storage in Beaver, UT · In queue since March 2022 · Proposed COD August 2024
80 MW
Capacity
1
Components
Battery
4y 4m
In Queue
IA Executed
IA Phase
COD target: 2024
Total Duration
2y 5m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-08-30
PacifiCorp-S0009 is a proposed 80 MW battery storage project located in Beaver County, Utah. The project, under development by Escalante BESS III LLC, entered the PacifiCorp interconnection queue on March 23, 2022, with a proposed commercial operation date of August 30, 2024.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Hickory substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Beaver
Grid Region
Mountain West
Market
—
Developer
Escalante BESS III LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Hickory substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-S0009Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.